Google, Nvidia, and Emerald AI found the AI Energy Management Alliance to support demand response capabilities within the data center sector
Joined by a range of launch partners, including Anthropic and RWE
Joined by a range of launch partners, including Anthropic and RWE
Company withdraws plans for Calvert Technology Center
Construction has commenced on two of the three buildings, with the third to be started next month
Would be located near the Calvert Cliffs Nuclear Power Plant
New development to be located next to Calpine’s Freestone Energy Center
Proposed campus within spitting distance of Limerick nuclear power station
Remains confident on the future of behind-the-meter deals with data centers
Initially slated for operations in 2028
Governor Hochul cited a need to achieve "energy independence" when announcing the plans
PPA is expected to facilitate a 30MW expansion at the Clinton Clean Energy Center
Oak Ridge National Laboratory, Elementl partner on nuclear site identification
Said there is ample opportunity to support data center development at significant scale
Company could seek grid based deals to power data centers
The acquisition will make Constellation the largest retail energy supplier in the US
US congressman Jay Obernolte argued that FERC should fast-track a clear rule set that will encourage the expansion of AI and its high energy requirements
Constellation has warned that the lack of clarity is impacting some of its plans to colocate data centers at nuclear power sites
Constellation believes narrow reforms are required to provide clarity, fair pricing, and price stability for customers and generators alike
DCFlex's founding members include some of the most preeminent players in the utility and data center markets
The NRC must finalize an environmental assessment within the last year before any restart
Site expected to return in 2028, in huge nuclear deal
Constellation, PSEG, and Vistra likely to ink deal with operators
Matched carbon-free energy brings facility close to round-the clock carbon-free energy
Company going ‘behind the meter’ at Wolf Hollow plant
Company already has one ‘behind the meter’ deal with Compute North, could target more