Archived Content

The following content is from an older version of this website, and may not display correctly.

KDDI owned colocation firm Telehouse Group will spend $140 m (11 billion Japanese yen) to expand its data center business in the China, Hong Kong and Taiwan markets.

The company is opening a new data center in Beijing, China, in December 2012 and at that time will expand its customer colocation space in Hong Kong.

Telecoms giant KDDI is working with web and data center services firm Sinnet to establish the joint venture in Beijing, known as Telehouse Beijing BDA Co - Both companies will operate the site.


KDDI operates four data centers in three cities in the Greater China Region, including Beijing, Shanghai and Hong Kong.

The Beijing data center will be the fifth Telehouse branded data center with the total floor area of 67,000 square meters (m2) in the region.

The second Beijing data center will be a carrier-neutral facility boasting a floor area of about 25,000 sq mts located in the city’s Technological Development Area (BDA).

In addition the Hong Kong CCC facility, which opened in 2011, will be further expand by 11,500 sq mts, making it one of the largest data centers in Hong Kong.

“KDDI and Telehouse America recognize Greater China as one of the most important growing markets, and leading the whole Asian economy,” comments Satoshi Adachi, VP of TELEHOUSE America.   “Additionally, active entry of Japanese, European and American companies requires world quality standards with high reliability services. In response, the KDDI group will support its customers’ business expansions by providing premier data center services and a high quality global network, using TELEHOUSE as its core, backed by the service advantages KDDI has in China with CD Networks (CDN) and DMX Technology.”

 

Specifications for the new TELEHOUSE Beijing data center are as follows:

 

Feature

Details

Location

Beijing Economic-Technological Development Area

Total floor area

About 25,000 (m2)

Power Receiving system

2 systems (standing & backup) receiving method

Private power generation

N1

UPS configuration

2N/N?1

CRAC

N20%

Water-cooling system

N1

Operation system

24-hour operation

Language

Chinese, English

Security

24 hour manned support, CCTV monitoring cameras, Contactless IC cards etc.

Basic service

Rack unit, Open and Caged colocation service

Option

Customer facility monitoring service

Customer work representative service