Cookie policy: This site uses cookies (small files stored on your computer) to simplify and improve your experience of this website. Cookies are small text files stored on the device you are using to access this website. For more information on how we use and manage cookies please take a look at our privacy and cookie policies. Some parts of the site may not work properly if you choose not to accept cookies.

sections

NSA data center 'crippled' by huge power surges

  • Print
  • Share
  • Comment
  • Save

A report in the WSJ.com said the US National Security Agency data center being built the US state of Utah has suffered a series of massive power surges which have crippled the facility and left contractors and investigators struggling to identify the root cause.
The article said the problems ‘delayed the center's opening for a year, according to project documents and current and former officials.
The project suffered 10 meltdowns in the past 13 months which led to the deployment of IT being delayed of stopped altogether. The electrical issues are arc faults with the causes still being investigated and the paper reporting ‘there is disagreement whether proposed fixes will work, according to officials and project documents.’
NSA spokeswoman Vanee Vines acknowledged to WSJ that problems existed but said "the failures that occurred during testing have been mitigated. A project of this magnitude requires stringent management, oversight, and testing before the government accepts any building."
The site is a 65 megawatt facility. The report said project documents show ‘backup generators have failed numerous tests,’ and that ‘cooling systems remain untested.’
The Army Corps of Engineers is overseeing the data center's construction and article quoted Chief of Construction Operations, Norbert Suter saying "the cause of the electrical issues was identified by the team, and is currently being corrected by the contractor." He said the Corps would ensure the center is "completely reliable" before handing it over to the NSA.
The proposed solutions are also a matter of dispute according to documents seen by WSJ with ‘the causes of eight of the failures haven't been conclusively determined. "We did not find any indication that the proposed equipment modification measures will be effective in preventing future incidents," said a report last week by special investigators from the Army Corps of Engineers known as a Tiger Team.’”
Balfour Beatty Construction, DPR Construction and Big-D Construction Corp are the joint venture constructing the site and architectural firm KlingStubbins designed the electrical system.
The joint venture said in a statement it expected to submit a report on the problems within 10 days: "Problems were discovered with certain parts of the unique and highly complex electrical system. The causes of those problems have been determined and a permanent fix is being implemented."
The factility is located in Bluffdale, Utah and spans one million sq ft. Each incident is said to have cause as much as $100,000 in damage. 
There remains disagreement as to the root causes and the proposed fixes between the Army Corps of engineers and the contractors, the WSJ said

Related images

  • nsa utah 2.jpg

Have your say

Please view our terms and conditions before submitting your comment.

required
required
required
required
required
  • Print
  • Share
  • Comment
  • Save

Webinars

  • Smart Choices for your Digital Infrastructure

    Tue, 28 Jun 2016 10:00:00

    Your data centre is a key part of successfully transforming and building your digital business. The challenge today is to create a highly reliable, flexible, scalable and cost-effective digital infrastructure. Your cabling system is an important element in the creation of that infrastructure. Attend and learn how to: - Piece together different elements of standards, technical specifications and physical properties in order to choose the right networking equipment - Reduce the time and labour spent maintaining, repairing or installing cabling by adopting improved design and management practices.

  • Designing Flexibility into your Data Center Power Infrastructure

    Wed, 4 May 2016 18:00:00

    As power density is rapidly increasing in today’s data center, provisioning the right amount of power to the rack without under sizing or over provisioning the power chain has become a real design challenge. Managing the current and future power needs of the data center requires Cap-Ex to deploy a flexible power infrastructure: safely handling peak power demands, balancing critical loads and easily scaling to meet growing power needs. In this webinar you will learn: > How to create Long term power flexibility and improved availability for your operation > How to increase energy efficiency and improve SLAs through a comprehensive set of best practices.

  • White Space 35: Signal to noise

    Mon, 18 Apr 2016 15:05:00

    In this weeks episode, we talk about networking records, Google’s outage and Amazon’s cloud dominance.

  • White Space 34: Open season

    Mon, 11 Apr 2016 13:15:00

    We talk open hardware, open source software and oxymorons.

  • White Space 33: All about Oregon

    Wed, 6 Apr 2016 08:35:00

    This weeks, White Space looks at news from the High Desert, and remember an American businessman who ran for president.

More link