Cookie policy: This site uses cookies (small files stored on your computer) to simplify and improve your experience of this website. Cookies are small text files stored on the device you are using to access this website. For more information on how we use and manage cookies please take a look at our privacy and cookie policies. Some parts of the site may not work properly if you choose not to accept cookies.


Snow cooling experiment in Japan melts away HVAC costs

Unusual data center has shown the viability of storing snow in winter and using it as a coolant in summer

Bibai City on Hokkaido, Japan’s northern island, has been working on the White Datacenter Project, a sustainability test site for using snow cooling in summer and venting off heat in the winter into greenhouses. The rest of the year, the data center is cooled by indirect air intake cooling.

In winter Bibai gets plenty of snow, between eight and 11 metres deep, but it has gone by the summer. Some of the townspeople decided it would be good to have snow in the hotter days of the summer and the Bibai Natural Energy Society and International Snow Club was formed.

Sapporo ice sculpture

Sapporo ice sculpture, Hokkaido

Source: SteFou! Flickr

Mounds of snow

The research group developed a system whereby the winter snow was heaped up into giant mounds and covered with chips of insulating material. In summer the snow melts slowly and the cold water is used for air conditioning systems.

The White Datacenter Project was born from this. In 2014, the New Energy and Industrial Technology Development Organisation (Nedo), a Japanese government R&D organisation, offered a five-year grant to investigate how snow removed from urban areas could be used to cool a datacenter.

In September 2015, a verification laboratory was opened: a single-storey, steel-frame data center covering 110.46 sq m and housing 20 racks of hardware. The building is equipped with a cold air intake and snow cooling system. Close by, a food production verification laboratory was built and this comprises a 155.52 sq m greenhouse, a plant factory, and an aquaculture facility.

In the latter half of last September a heat exchanger system under the snow mound was used to cool the data center. Snow cooling maintained the ambient temperature of the building at 25C without the need for electric air cooling. In February, the indirect air cooling system had taken over and the exhaust heat was used to maintain temperatures in the agricultural buildings. Even in midwinter a minimum temperature of 15C was maintained using server exhaust heat alone.

Pue Results

Source: White Datacenter Project

The initial results of the White Datacenter Project are encouraging (see PUE results table). Scaled up to a 3,000 rack facility and compared with data centers based in Tokyo, 1,000km (620 miles) south of Bibai, the White Datacenter is expected to show improved HVAC charges. The research team reckon this would be approximately 80 percent less than a traditional data center and 54 percent less than one with centrifugal chillers.

The test center is based in Sorachi Industrial Park in Bibai and it is hoped snow cooling will attract several companies to set up larger data centers on the 94 hectares (232 acres) site.

Readers' comments (1)

  • Have you not heard of theHospital in Sundsvall, Sweden